How Chinese Pipe Fitting Manufacturers Ensure On-Time Delivery for EPCs

On-Time Delivery Is a Managed Engineering System, Not a Quotation Promise

For Engineering, Procurement, and Construction (EPC) contractors managing mega-projects in petrochemical, power, LNG, and offshore sectors, a pipe fitting delay is never isolated. Sourcing elbows, tees, reducers, and forged components requires aligning engineering data, material heat approvals, quality inspection holds, and multi-modal transit.

10Gates

Milestone Verification

Production lead times cannot rely on a single date. They depend on ten independent, auditable control gates.

100%Trace

Heat & MTC Alignment

Full traceability from raw billet/seamless tube to final EN 10204 3.1/3.2 certificates prevents dock rejections.

ZeroSurprises

Hold-Point Synch

Advance alignment with Third-Party Inspection agencies (TPIA) prevents finished goods from waiting at the factory gate.

DDP/FOBParity

Incoterms Distinction

Ex-works readiness must not be mistaken for Required-On-Site (ROS) project deadlines.

Crucial Distinction: Ex-Works vs. Required-On-Site (ROS) Dates

A qualified Chinese manufacturer acknowledges that when an order is technically formed, finished, and hydro-tested, delivery is not finished. Presenting a factory's ex-works manufacturing duration as equivalent to delivery at an international EPC site is the most frequent source of schedule failure. Inspection notice buffers, customs clearance, sea-freight transit, transshipment risks, and port handling must be built into the critical path schedule.

 
1. RFQ & Technical Clarification Closure
Freezing standard deviations, wall thickness schedules, client Approved Vendor List (AVL) requirements, and testing parameters.
 
2. Drawing Approval & Release for Manufacture (RFM)
Formal authorization of non-standard fittings, special bevel configurations, and nozzle interfaces via signed Drawing Registers.
 
3. Raw Material Allocation & Heat Verification
Physical receipt and quarantine testing of seamless mother pipe, plate, or forging billets with EN 10204 3.1 chemical verification.
 
4. Forming, Heat Treatment & Machining
Hot-mandrel pushing, cold extrusion, induction heating, solution annealing, normalizing, and CNC bevel machining.
 
5. QA/QC, ITP Hold Points & TPI Release
NDT (RT/UT/MT/PT), PMI testing, hydrostatic inspection, dimension tolerance verification, and Third-Party Inspection sign-off.
 
6. Dossier Sign-Off, Export Packing & Port Dispatch
Final Manufacturing Record Book (MRB) approval, seaworthy crating, end-cap bevel preservation, customs filing, and freight dispatch.

Stage 1: Complete RFQ Specifications Before Quotation

An incomplete Request for Quotation (RFQ) never accelerates an EPC schedule. Instead, it merely defers technical engineering clarification to the manufacturing stage, when resolving ambiguities introduces severe disruption, idle mill capacity, or scrap.

Common RFQ Omission Downstream Technical Delay Cause Preventive Mitigation Protocol
Incomplete Fitting End Preparation
Machining
Unspecified transition tapers or custom weld bevels (e.g., ASME B16.25 Compound Bevels vs. ASME B31.3) stop machining operations. State exact matching pipe wall schedule, OD/ID tolerances, and require preliminary bevel profile sign-off prior to order acceptance.
Unstated NDT & Corrosion Testing
Testing
HIC (NACE TM0284), SSCC, or mandatory 100% radiographic examination requested late requires additional test coupons and subcontracted laboratory queues. Provide project supplementary specification (e.g., ISO 15156/NACE MR0175, cryogenic impact testing at -196°C) at the initial RFQ stage.
Generic Material Standard (e.g., "A234 WPB")
Metallurgy
Failure to indicate restrictive carbon equivalent (CE), heat treatment mode (N, N&T), or maximum hardness limits halts raw material procurement. Supply comprehensive project design engineering data sheets specifying all supplementary chemical and mechanical requirements.
Unspecified Inspection Level (EN 10204 3.1 vs. 3.2)
Documentation
Switching from manufacturer-certified 3.1 to independent third-party 3.2 inspection late invalidates already forged stock lacking witness heats. Mandate clear documentation class in the line-item schedule; allocate appointed TPIA (e.g., Lloyd's, DNV, SGS, TÜV) before PO award.

Technical Clarification Register (TCR)

Top Chinese pipe fitting manufacturers enforce an upfront Technical Clarification Register prior to PO acceptance. If an EPC request contains standard conflicts (e.g., ASME B16.9 vs. DIN EN 10253 or MSS-SP-75 tolerances), technical engineers flag them immediately, establishing clear solutions before material procurement.

Scope Boundaries for Custom Items

Barred tees, lateral tees, split sleeves, and high-yield heavy-wall wyes demand hydraulic simulations and specific tooling. Early technical clarification verifies whether specialized dies, mandrels, or sub-tier forging capabilities are ready, preventing unexpected engineering holds midway through production.

Stages 2 & 3: Drawing Registers & Raw Material Allocations

Delays in drawing reviews and ambiguous material sourcing represent major failure points for custom fitting packages. High-performing manufacturing facilities isolate these risks through controlled drawing registers and multi-tier raw material traceability.

Drawing Register Discipline

Non-standard fittings must not proceed on informal email exchanges. Manufacturers implement formal Drawing Registers recording: Drawing ID, Revision index, Client Comment Return Date, and Release For Manufacture (RFM) signatures to stop unauthorized variance.

Material Readiness Tiers

"Material Available" is often used loosely. Professional suppliers categorize inventory into four distinct states: In General Factory Stock, Mill Order Placed, Raw Ingot Received Under Quarantine, and Heat-Assigned Stock Approved for the specific PO.

Alloy & Heat Segregation

Stainless steels (304L/316L), Super Duplex (2507/2205), and Nickel Alloys (Inconel 625, Hastelloy) require physical isolation to prevent cross-contamination. Heat numbers must be preserved through stamping, laser marking, or paint stencil transfers at every cut.

Managing Scrap & Rejection Buffers for Critical Alloys

Forging large-diameter heavy-wall elbows or extruding extruded tees from specialized titanium or high-nickel alloys carries inherent yield losses. Experienced Chinese manufacturers procure a calculated 5% to 10% material buffer on raw billets or mother tubes. If a destructive test coupon fails grain size or tensile metrics, a pre-allocated backup heat is immediately released, avoiding standard 8-to-12-week steel mill re-melt lead times.

Stage 4: Production Routing, Milestone Scheduling & Capacity Controls

Converting a project order into an achievable production plan requires matching line capacity across distinct production paths. Buttweld elbows, forged branch outlets (weldolets), and induction bends follow different shop-floor routes with unique machine constraints.

Milestone Phase Required Verification / Evidence Critical Path Schedule Risk Mitigation Mechanism
1. Technical Freeze & PO Launch Signed ITP, approved deviations, confirmed line items. Scope gaps; unresolved engineering comments. Pre-production kick-off meeting with clear issue ownership.
2. Drawing Register Sign-Off Approved for Construction (AFC) fabrication drawings. Revision churn on special-dimension bevels. Set a 5-day review deadline; expedite via design lead.
3. Billet / Pipe In-House Receipt Mill Test Certificates; Positive Material Identification reports. Sub-tier mill late deliveries or grade rejections. Audit reserve inventory; engage qualified backup steel mills.
4. Forming & Extrusion Process Shop floor traveler sheets; batch progress reports. Hydraulic press or furnace capacity bottlenecks. Shift allocation; routing across dual pushing lines.
5. Solution / Normalizing Heat Treatment Calibrated time-temperature charts; thermocouple logs. Furnace queue backlogs; cycle temperature variances. Batch scheduling; dedicated qualified thermal cycles.
6. CNC Machining & Bevel Finishing Bevel angle profile logs; laser caliper dimension records. Tooling downtime on hard duplex/alloy steel grades. Pre-tooled high-speed CNC centers with reserve tool arrays.
7. QA/QC & ITP Hold-Point Execution Signed ITP check sheets; NDT (RT/UT/MT/PT) logs. TPI surveyor scheduling conflicts. Formal 7-day advance booking notice with TPI agencies.
8. Manufacturing Record Book (MRB) Completed quality dossier, MTCs, heat records. Clerical mismatch of heat numbers vs. pipe markings. Real-time concurrent QA documentation during production.
9. Export Preservation & Packing Photographic packing logs; export crating checklists. Improper seaworthy crating or missing item tagging. Barcoded steel/wooden crate packaging with ISPM 15 compliance.
10. Freight Booking & Customs Dispatch Shipping Order (SO), forwarder receipt, Bill of Lading. Blank sailings, container shortages, customs hold. Book shipping slots 14 days before final release.

Stages 5 & 6: QA/QC Without Last-Minute Shocks: ITPs, MTCs & Third-Party Inspection

Speeding up production lines cannot fix a project delayed by quality issues. If a pipe fitting fails hydrostatic pressure, shows laminations during ultrasonic testing, or has a mismatched heat number, pushing shop floor speed only results in scrapped batches. Quality controls must be woven directly into the timeline.

MTC & MTR Authenticity

EN 10204 Type 3.1 or 3.2 Material Test Certificates must match product stampings, heat numbers, chemical composition tests, and mechanical tensile logs. Discrepancies here will halt destination port customs clearance.

Inspection & Test Plan (ITP)

Define Witness (W), Hold (H), and Review (R) inspection gates before production begins. Hold points stop further manufacturing until the EPC inspector or nominated TPIA surveyor formally signs the inspection release note.

TPIA Advance Booking Protocols

Third-Party Inspection agencies (e.g., DNV, BV, SGS, TÜV, Intertek) experience resource constraints. Competent Chinese suppliers manage a rolling 7-day lookahead notification window to prevent idle product queues.

Technical Insight: Resolving Quality Delays

Accelerating production while facing unresolved defects is the primary cause of major project delays. If an alloy elbow batch exhibits micro-cracking during cold forming, running additional units through the furnace increases material loss. The reliable approach is pausing the run, conducting Root Cause Analysis (metallurgical grain size, forming temperature rate), adjusting the parameters, and qualifying a test piece before continuing.

Stages 7 & 8: Documentation Dossiers, Heavy Packing & Logistics Coordination

Finishing machining and factory painting does not mean an order is ready for dispatch. In international EPC supply chains, documentation oversights hold goods at port docks just as easily as physical defects.

The Pre-Dispatch Document Dossier

Shipments should not leave the facility until the Quality Dossier is complete and verified:

  • Material Test Certificates (EN 10204 3.1 or verified 3.2 by appointed TPIA).
  • NDT Examination Reports (RT films, UT scans, PT inspection records).
  • Heat Treatment Time-Temperature strip charts and calibration certs.
  • Dimensional inspection sheets and Hydrostatic test certificates.
  • Detailed commercial invoice and itemized packing list reconciling crate numbers.
  • Preferential Certificate of Origin (CO) documentation where applicable.

Engineered Packing & Bevel Protection

Pipe fittings are vulnerable during intermodal ocean transport. Export packaging must ensure:

  • Bevel protection via heavy-duty plastic end-caps, metal protectors, or wooden plugs.
  • Rust-preventative coatings: rust-inhibitive varnish, black painting, or light oil.
  • Separation of austenitic stainless steels from carbon steel handling bands to prevent iron contamination.
  • Sturdy fumigated wooden crates (ISPM 15 certified) or steel-framed skids.
  • Clear weatherproof shipping markings matching the EPC packing list items.

Stages 9 & 10: Quantitative Expediting & Proactive Delay Recovery

Effective expediting does not mean repeatedly sending emails asking "Is the order ready?" Professional project expediting involves tracking whether each milestone gate is meeting its schedule, confirming status with photographic and physical evidence, and catching variance early.

Structured Expediting Status Reports

Weekly expediting logs should record:

  • Actual percentage of forming, heat treatment, and beveling completed per line item.
  • Open technical queries (TQ) with specific assigned owners.
  • Third-party inspection booking reference and inspector attendance date.
  • Raw material heat allocation updates with mill test certificate copies.
  • Current estimated ex-works completion date compared to the baseline schedule.

The 8-Step Delay Recovery Protocol

When a critical milestone is missed, disciplined manufacturers follow a structured escalation path:

  1. Identify the specific technical or operational root cause of the delay.
  2. Isolate confirmed shop floor realities from broad assumptions.
  3. Map affected line items against the EPC contractor's installation critical path.
  4. Evaluate re-sequencing (e.g., forming priority items while other drawings clear).
  5. Introduce split-shipment options: dispatch high-priority piping spools first.
  6. Add qualified overtime machining shifts or switch to parallel CNC work centers.
  7. Publish an updated milestone schedule baseline within 48 hours.
  8. Monitor recovery milestones daily until the schedule variance is resolved.

EPC Delivery-Risk Control Matrix

Use this risk matrix during pre-award supplier technical audits and post-award project tracking to identify potential delays and establish concrete preventive and recovery controls.

Potential Delay Phase Early Warning Sign Preventive Control Strategy Practical Recovery Action
Incomplete RFQ Scoping Repeated technical queries regarding wall schedule, bevel details, or design pressure. Standardized RFQ completeness audit prior to commercial price finalization. Hold a dedicated clarification conference; assign owners to resolve open items within 48 hours.
Drawing Revision Cycles Multiple revisions on custom wye or barred tee drawings without sign-off. Formal Drawing Register establishing clear client review deadlines. Freeze unapproved dimensions; release approved standard line items for production first.
Raw Material Sourcing No formal mill order confirmation or mill heat batch certificate provided. Validate raw material inventory reservations; require mill order confirmation copies. Source pre-inspected certified stock material from qualified master distributors.
Shop Floor Forming Holds Shop progress reports show identical completion percentages across multiple weeks. Weekly photographic verification linked directly to individual line items. Re-sequence manufacturing runs; allocate dual hot-forming lines and secondary CNC machines.
QA/QC Nonconformance High scrap rates during hydrostatic pressure testing or non-destructive examination. Perform early incoming raw material checks and test sample pieces before main runs. Isolate affected heats, adjust heat treatment recipes, and process verified reserve stock.
TPIA Booking Delays Surveyor has not confirmed attendance 48 hours prior to the scheduled hold point. Establish a 7-day lookahead notification window in the project Inspection and Test Plan. Escalate via regional TPIA management; coordinate an approved proxy surveyor.
Documentation Gaps Material certificates or NDT reports missing required customer witness signatures. Maintain a progressive document dossier that compiles records alongside production. Dedicate an on-site QA engineer to complete documentation before crating begins.
Export Logistics Stalls Shipping container booking unconfirmed while fittings sit in the packing area. Secure shipping space 14 days prior to estimated factory completion date. Reroute to alternative departure ports or switch from sea-freight to air/multimodal for urgent items.

Illustrative Project Scenario & Supplier Capability Verification

Consider an illustrative scenario demonstrating milestone-based delivery management for an EPC contractor sourcing high-pressure piping components under tight project deadlines.

Scenario: Managing Material Delays on an LNG Plant Fitting Package

Context: An EPC order covers 2,400 buttweld fittings, comprising standard A234 WPB carbon steel elbows and 320 custom heavy-wall ASTM A815 S32750 Super Duplex tees and reducers for an LNG expansion project.

The Challenge: During week 4, the primary specialty mill notifies the factory that the super duplex mother pipe delivery will be delayed by 21 days due to billet extrusion maintenance. Concurrently, drawing revisions for two large-diameter barred tees remain unresolved with the EPC engineering team.

The Mitigation Response: Rather than waiting for complete package readiness, the manufacturer activates an early recovery protocol:

  • Package Splitting: The carbon steel package (2,080 standard items) proceeds on its original schedule, passing TPIA hold points without delay.
  • Inventory Allocation: The manufacturer sources certified reserve S32750 seamless mother pipes from an audited master stockholder to start tee production early.
  • Drawing Register Escalation: The engineering team issues a formal query notice, securing approval for the barred tee internal grid drawings within 48 hours.
  • Phased Shipping: Carbon steel fittings ship via sea-freight on the original schedule; duplex items complete production under an added shift, shipping as an approved second consignment to meet the site's spaded hydrotest deadline.

How to Verify a Supplier's Delivery Capabilities

Before issuing a major pipe fitting purchase order, request concrete evidence of operational control rather than generic marketing statements:

1. Milestone Schedule Records

Request an anonymized milestone schedule from a completed project. Verify that it tracks separate dates for material receipt, forming, NDT testing, TPIA release, and document sign-off.

2. In-House Manufacturing Scope

Clarify which operations take place in-house and which are subcontracted (e.g., hot induction forming, heat treatment, specialized machining, NDT). High subcontracting ratios require closer expediting oversight.

3. Heat Traceability Protocols

Review physical marking systems, material transfer logs, and EN 10204 3.1/3.2 certificate reconciliation methods to ensure markings remain fully traceable through all manufacturing steps.

Pre-Award Buyer Checklist & Standard RFQ Schedule Template

Use this checklist and template to structure your procurement requests and build contractual clarity into the delivery schedule before issuing a purchase order.

EPC Buyer Checklist: Prior to Purchase Order Finalization

  • Applicable dimensional & manufacturing specifications defined (ASME, EN, MSS-SP, DIN).
  • Matching pipe schedule, wall thickness tolerances, and bevel transition tapers confirmed.
  • Material grade, supplementary requirements (NACE, low-temp impact, CE limits) specified.
  • Inspection certificate class clarified (EN 10204 Type 3.1 vs. Type 3.2 with designated agency).
  • Approved Inspection and Test Plan (ITP) witness and hold points formally agreed upon.
  • Raw material allocation confirmed (quarantined stock vs. new mill production with run dates).
  • Lead-time anchor established (measured from PO award, technical freeze, or drawing sign-off).
  • Seaworthy export packaging, marking, and rust-preservation specifications confirmed.
  • Agreed Incoterms rules, port of origin, and logistics hand-off requirements documented.
  • Escalation paths, weekly progress reporting cadences, and delay recovery plans defined.

Standard RFQ Delivery-Schedule Request Template

Incorporate the following clause directly into your RFQ packages to obtain reliable, comparable schedule commitments from prospective pipe fitting manufacturers:

BIDDER SCHEDULE & MILESTONE COMMITMENT CLAUSE:

1. Bidder shall provide an itemized milestone schedule showing: (a) Technical clarification closure, (b) AFC drawing submission/approval, (c) Mother pipe/billet arrival, (d) Hot/cold forming, (e) Heat treatment, (f) Machining, (g) ITP hold points / TPI inspection, (h) MRB dossier sign-off, (i) Export packing, and (j) Factory dispatch readiness.

2. Bidder shall state the precise trigger event from which manufacturing lead times are measured (e.g., PO receipt, LC opening, or final drawing approval).

3. Bidder shall disclose raw material source assumptions: indicate whether material is currently in company stock, requires procurement from an approved master mill, or involves custom forging ingots.

4. Bidder shall confirm acceptance of weekly expediting reports and agreement to the owner's 7-day advance notification protocol for TPIA inspection hold points.

5. Bidder shall identify any exceptions or technical deviations to the inquiry specifications in a formal Technical Deviation Schedule. Unstated deviations will not be accepted post-award.

A Promised Delivery Date Is Only as Credible as Its Supporting Milestones

In large industrial projects, schedule confidence does not come from optimistic quotation assurances. A promised delivery date becomes reliable only when it is supported by a documented sequence of verifiable engineering, procurement, testing, and documentation milestones.

Visibility Preserves Recovery Options

The earlier a schedule variance is recognized, the more options the project team retains to protect the timeline. A raw material delay identified during week 2 can be mitigated by allocating reserve stock or re-sequencing runs. The same delay identified after goods miss a shipping window leaves air freight as the only—and costly—recourse.

Disciplined Coordination Drives Predictability

External variables like weather, port congestion, and customs clearance will always exist. However, by enforcing clear RFQ specifications, maintaining disciplined drawing registers, validating material allocations, and coordinating third-party inspections in advance, EPC contractors and Chinese pipe fitting manufacturers can build dependable supply chains that deliver projects on schedule.

32ft x 10ft Anti Vandal Canteen/Office

  • Complete with tables and chairs
  • Kitchen with sink worktop, cupboard and water heater
  • Insulated with electric sockets, lighting and heating
  • White upvc double glazing
  • External re spray in dark grey

Location: Nationwide

£6,500 + vat

Not Available for Hire

We can deliver for a cost please ask and send us post code.

Call for an instant quote!

Steel Cabin Staircases, in various sizes

  • 13 tread

  • 14 tread

  • 15 tread

Location: Nationwide

£1,200.00 + vat

Not Available for Hire

Call for an instant quote!

32ft x 10ft Anti Vandal Canteen/Office

    • Price: £5,995 + VAT
    • Description: 32ft x 10ft Anti Vandal Canteen/Office
  Part refurbished including:
  • Electric sockets, lighting and heating
  • White upvc double glazing
  • Canteen
  • Open plan
  • External light grey re spray

Location: Nationwide

£5,995 + vat

Not Available for Hire

We can deliver for a cost please ask and send us post code.

Call for an instant quote!

32ft x 10ft Drying Room, Toilet Block

Hallway leading into:

  • Price: £6,500 + VAT
  • Half open plan drying room, or we could add in a canteen. (additional cost)
  • Female Single toilet
  • Male toilets including 2 x cubicles, 2 x urinals and 2 x sinks
  • External light grey spray
  • Deep cleaned
  • Ready to use
  • Excellent overall condition

Transport can be arranged please ask.

Location: Nationwide

£6,500.00 + vat

Not Available for Hire

Call for an instant quote!

  • 20ft x 8ft Container Conversion Retail Shop

  • UPVC Double glazed Windows + French Doors

  • Slat Wall for retail fixings and Merchandise

  • Electric Chrome Sockets, led lighting and heating.

  • Laminate Flooring

  • 12 months Warranty

  • Maintenance call out package included

  • Less than 2 years old

  • Still in Brand New Condition

Location: Nationwide

POA

Not Available for Hire

Call for an instant quote!

32ft x 10ft Jack Leg Cabin

  • Fully refurbished

  • Colour light grey

  • Slate grey anthracite upvc double glazed windows

Location: Nationwide


£15,000

+ VAT

Not Available for Hire

Call for an instant quote!

20ft x 8ft Container Office

  • Fully Insulated with electric sockets, spot lighting, and heating

  • Wood Flooring

  • UPVC Sliding Door + Windows

  • Lead Time for build 6-8 weeks

Location: Nationwide


£12,995.00

+ VAT

Not Available for Hire

Call for an instant quote!

20ft x 8ft Container Office

  • Fully Insulated with electric sockets, spot lighting, and heating

  • Wood Flooring

  • Aluminium Bi Fold Doors

  • Fully wrapped in larch cladding

  • Lead Time for build 6-8 weeks

Location: Nationwide


£16,500.00

+ VAT

Not Available for Hire

Call for an instant quote!

10ft x 8ft Container Conversion

  • Fully Insulated with electric sockets, spot lighting, and heating

  • Wood Flooring

  • Feature Clad Wall and Ceiling

  • UPVC Double glazed French Doors

  • Fully wrapped in larch cladding

  • Lead Time for build 6-8 weeks

Location: Nationwide


£12,500.00

EX VAT

Not Available for Hire

Call for an instant quote!

40ft x 8ft Rooftop Container Bar

  • 40ft x 8ft Rooftop Container Bar
  • Fully Insulated with electric sockets, spot lighting, and heating
  • Built in Bar
  • Wood Flooring
  • Feature Larch Clad Wall
  • Aluminium double glazed premium windows and double French doors
  • Fully wrapped in larch cladding
  • Steel staircase up to Rooftop terrace with full surrounding steel balustrade
  • Double container doors leading to cool room with Air Conditioning unit.
  • Lead Time for build 6-8 weeks

Location: Nationwide


£85,000.00

EX VAT

Not Available for Hire

Call for an instant quote!

  • Fully Refurbished
  • Zinc Roof
  • Colour Light Grey (Other Colour Options Available)
  • New Flooring
  • New Electric Sockets, Lighting and Heating
  • New UPVC Large and Small Windows
  • New Kitchenette with Partition
  • New Toilet Room with toilet, Sink, Water Heater and Fan

Location: Nationwide

£18,995

EX VAT

Not Available for Hire

Call for an instant quote!

6 x 21ft x 8ft Container Stores

  • Wind and Water Tight
  • Very Good Condition
  • Some have racking inside
  • Floorings all good
  • Contents not included

Location: Nationwide


£1,500

EX VAT

Not Available for Hire

Call for an instant quote!

32ft x 10ft Anti Vandal Canteen in Blue

  • Used with electric sockets, lighting and heating
  • UPVC Double Glazed Windows
  • Furniture
  • Kitchenette 

Location: Nationwide


£4,995

EX VAT

Not Available for Hire

Call for an instant quote!

20ft Used Shipping Containers

  • Wind and Water Tight
  • Doors in good working Order
  • Random Selection
  • Lock Box and Lock additional cost.

Location: Nationwide


£1,500

EX VAT

Not Available for Hire

Call for an instant quote!

24ft x 10ft Jack Leg Anti Vandal Canteen/Toilet/Storage

  • Split entrance for Canteen room and WC which includes single cubical, urinal and sink.
  • Container door end with storage.
  • Electric Sockets, Lighting and Heating
  • Fitted Floor to Ceiling Cupboards
  • Colour: Dark Green

Location: Nationwide


£5,000

EX VAT

Not Available for Hire

Call for an instant quote!

40ft x 12ft Jack Leg Genuine Portakabin Pullman

  • 2 x Offices, Canteen and WC
  • Electric Sockets, Lighting and Heating
  • Colour: Light Grey
  • Full or Part Refurbishment option is available please ask.

Location: Nationwide


£9,500

EX VAT

Not Available for Hire

Call for an instant quote!

32ft x 10ft Anti Vandal Split Canteen/Office

  • Canteen approx 10ft – Office approx 22ft
  • Electric Sockets, Lighting and Heating
  • UPVC Double Glazing
  • Colour: Dark Blue

Location: Nationwide


£5,500

EX VAT

Not Available for Hire

Call for an instant quote!

8ft x 8ft Anti Vandal Gate House/Office

  • Open Plan
  • Electric Sockets, Lighting and Heating
  • Colour: Clad in New Larch Timber

Location: Nationwide


£5,500

EX VAT

Not Available for Hire

Call for an instant quote!

20ft x 10ft Anti Vandal Sleeper Unit

  • Split sides with two entrances, each side has its own room and Shower Toilet Facility
  • Electric Sockets, Lighting and Heating
  • Colour: Dark Grey

Location: Nationwide


£6,500

EX VAT

Not Available for Hire

Call for an instant quote!

21ft x 8ft Anti Vandal Canteen

  • Open Plan
  • Electric Sockets, Lighting and Heating, Hot water Unit + kitchen with cupboards and work top.
  • Colour: Dark Grey 

Location: Nationwide


£4,200

EX VAT

Not Available for Hire

Call for an instant quote!

30ft x 9ft Anti Vandal Fire Rated Office

  • Open Plan Refurbished
  • Electric Sockets, Lighting and Heating
  • Colour: Dark Blue

Location: Nationwide


£6,500

EX VAT

Not Available for Hire

Call for an instant quote!

24ft x 9ft Anti Vandal Office

  • Open Plan
  • Electric Sockets, Lighting and Heating
  • Colour: Dark Grey

Location: Nationwide


£4,200

EX VAT

Not Available for Hire

Call for an instant quote!

22ft x 9ft Jack Leg Portable Cabin

  • 22ft x 9ft Jack Leg Portable Cabin
  • Open Plan
  • Electric Sockets, Lighting and Heating
  • Fitted Desk and Floor to Ceiling Cupboards
  • Colour: Light Grey

Location: Nationwide


£4,995

EX VAT

Not Available for Hire

Call for an instant quote!

24ft x 9ft Jack Leg Portable Cabin

  • 24ft x 9ft Jack Leg Portable Cabin
  • Split Offices with two entrances
  • Electric Sockets, Lighting and Heating
  • Fitted Floor to Ceiling Cupboards
  • Colour: Light Grey

Location: Nationwide


£5,500

EX VAT

Not Available for Hire

Call for an instant quote!

10ftx8ft – £5950 + Vat / 16ftx8ft – £7950 + Vat / 20ftx8ft – £9000 + Vat / 24ftx8ft – £12000 + Vat / 30ftx8ft – £13500 + Vat

  • Reinforced doors and windows with secure locking
  • Open plan with electric sockets and lighting
  • Any Extras available: Canteen, Partitions, Toilets.

Location: Nationwide


From £5,950

EX VAT

Not Available for Hire

Call for an instant quote!

  •  Electric Sockets, Lighting and Heating
  •  Wind & watertight
  •  Sprayed Dark Grey

Location: Nationwide


£4,995

EX VAT

Not Available for Hire

Call for an instant quote!

  • 12ft Towable Gound Hog
  • Includes: toilet, canteen and seating area
  • Full working generator, fully serviced and in great condition

 

Location: Nationwide


£6,500

EX VAT

Not Available for Hire

Call for an instant quote!

  • Reinforced doors with secure locking 
  • Electrics and lights included
  • Sink and water boiler included

Location: Nationwide

Quantity: ∞

£15,000

EX VAT

Not Available for Hire

Call for an instant quote!

• Reinforced doors and windows with secure locking
• Open plan with electric sockets and lighting
• Ral Code Colour of choice

• Any Extras available : Canteen, Partitions, Toilets.

Location: Nationwide


£11,995

EX VAT

Not Available for Hire

Call for an instant quote!

• Reinforced doors and windows with secure locking

• Open plan with electric sockets and lighting

• Ral Code Colour of choice

• Any Extras available : Canteen, Partitions, Toilets.

Location: Nationwide


POA

Not Available for Hire

Call for an instant quote!

test

• Reinforced doors with secure locking
• Sink and water boiler included

Location: Nationwide

Quantity: ∞

£12,495

EX VAT

Not Available for Hire

Call for an instant quote!

32ft x 20ft Cabin

  • Reinforced doors with secure locking 
  • Electrics and lights included
  • Sink and water boiler included
  • Electric Roller Shutters
  • Roof top terrace 
  • Store Room 
  • Slatwall installation 

Location: Nationwide


£39,000

EX VAT

Not Available for Hire

Call for an instant quote!

Looking to Buy or Hire?

Get a Quick Container Quote Now!

20ft x 8ft Container Kiosk

  • Open plan layout with worktop serving area
  • Electric roller shutter with remote control
  • Electrics and lights included

Location: Nationwide

 

£15,000

EX VAT

Not Available for Hire

Call for an instant quote!

Looking to Buy?

Get a Quick Container Quote Now!

Newsletter Signup Form

Be the first to discover our exclusive offers and latest company updates by signing up to our email newsletter. Every month we’ll keep you informed of our best prices, industry updates, customer’s container projects, national shows we’ll be exhibiting at, and much more.

Looking to Buy or Hire?

Get a Quick Container Quote Now!